- Feb. 1: Opening of temporary Amtrak Station at 1800 21st Street.
- Feb. 1: Closure of the pedestrian tunnel from the historic station to the current light rail platform and Mall Shuttle stop.
- Feb. 9: Closure of the Bus/HOV lane behind Union Station and re-routing of peak hour Regional and Express buses to Market Street Station.
- Spring 2011: Construction of Chestnut Place.
- Summer 2011: Opening of the new Light Rail Station and the extension of the 16th Street Mall Shuttle to the station.
- Summer 2011: Closure of Wewatta Street behind Union Station and opening of Chestnut Place.
- Summer 2011: Construction will begin on the next phase of the underground bus facility from Wewatta Street to the west side
of the historic Denver Union Station building. - Ongoing: Continued utility relocation.
- Ongoing: Work on the interior of the current phase of the underground bus facility.
Stay tuned for more updates!